Saturday, July 18, 2009

More roofing

One tricky thing about building on a hill, you can't get a great shot of the roof:


Siding nearly completed on all sides:


Flashing for the deck installed:


The door to the deck is cut through the insulation:


Garage siding is nearly complete:

Friday, July 17, 2009

Roofing materials

Roofing materials arrive on-site:

Thursday, July 16, 2009

Insulation

Vapor barrier on the ceiling of the master bedroom:


Batting around the wood stove stack:


Batting around the dining room ceiling.


Next: Windows! We ain't talking software either!

Wednesday, July 15, 2009

2nd Floor, Siding, Insulation

Additional trim around the house:


2nd floor is complete, ready for flooring once windows and drywall are in place. Sidewall insulation going in:


Siding along one wall nearly complete. The square that is incomplete is the probable location of some electrical gear including the generator for long periods without solar or wind.


Looking along the wall, insulation being installed in the 1st floor:


Locked down counter top colors today. Hope to lock down flooring selections in the next couple of days. Continue working on light fixture selections.

Tuesday, July 14, 2009

Past four days...

More siding...


Radiant heat for the master bedroom:


Radiant heat 2nd floor kitchen, dining room, and living room. Gypsum will be poured over the tubing. Maybe another layer of plywood and then the flooring.


Power left, coax and telephone right. Most of the electrical rough in is complete. Wires are now trimmed back to respective locations. Where the big AC wire is going is still a little up in the air...


More siding:


And more siding... looking like a house there, eh? Some say a true Alaskan house is one where there is everything but the siding :)


Siding wrapping around the front to the plug-in on the garage:


Now that the electrical is squared away (almost; still trying to work out where the generator, batteries, inverter and other equipment will go) the windows need to be installed. Once the windows are in, then some 2nd floor ceiling insulation needs to be done. A layer of batting needs to be put down into the vaulted ceiling and finished off with some cellulose to be blown in. We hope for a little cooler weather!
  • Electrical (wrap up)
  • 2nd Floor ceiling insulation (batting and cellulose)
  • Drywall
  • Cabinets, counters
  • Plugs, lights, switches
  • Appliances (Washer, Refrigerator, Stove)
  • Heating, HRV, etc
  • Wind, solar, batteries, inverter and generator... possibly all stashed away in an external shed.
We'll see what order this all shakes out.

Thursday, July 9, 2009

Siding, wiring and window framing! Oh my!

All large materials are in, holes on the garage side are filled in and have a vapor barrier installed.


Window frame:


Kitchen wiring:


Siding:


View from Dining Room window into the valley, not quite the clearest night. It is comparatively clearer than the rest of this past week with the forest fire to the SW of us.


View from Living Room window into valley:


Next? Finish up the rough ins (wiring). Insulating the ceiling and drywall?

Wednesday, July 8, 2009

Progress

6 inch insulation complete, another frame is put in place:



HRV ducting:


Septic about finished, 6 zones of heating:


Site visit tomorrow AM to cover lights and electrical outlets. Heavier smoke moved in from Minto Flats. Expecting a bit of rain to hope clear it out tonight as well.

Map of Minto Flats fire to the south and west of Murphy Dome: